Northern: Rolling Stock:Written question - HL16845

Q
Asked by Lord Scriven
Asked on: 01 July 2019
Department for Transport
Northern: Rolling Stock
Lords
To ask Her Majesty's Government why it will not be possible to complete the removal of Pacer trains from the Northern rail network by 31 December.
A
Answered on: 12 July 2019

Northern Rail is planning to remove the first pacer in August, and is working to remove all of the pacers by the end of the year. Due to delays in manufacturing of new trains, a small number of pacers may continue on the network into the beginning of the new year to ensure a stable service for passengers.

Our absolute priority is ensuring passengers in the north benefit from new trains, more services and increased capacity as quickly as possible. People across the north are starting to see new trains across the network, alongside the extra 2000 services a week already delivered.