Buildings: Insulation:Written question - 66814

Q
Asked by Hilary Benn
(Leeds Central)
[N]
Close

Named Day

'Named day' questions only occur in the House of Commons. The MP tabling the question specifies the date on which they should receive an answer. MPs may not table more than five named day questions on a single day.

Asked on: 30 June 2020
Ministry of Housing, Communities and Local Government
Buildings: Insulation
Commons
To ask the Secretary of State for Housing, Communities and Local Government, what the timeframe is for the removal of all unsafe cladding from residential buildings.
A
Answered by: Christopher Pincher
Answered on: 06 July 2020

Building safety is the responsibility of the building owner, and we expect remedial works to progress at pace.

For the removal of unsafe ACM cladding from high-rise residential buildings the Government has provided £600 million in funding. We have made progress, and as a result of our action, across all sectors, 209 buildings have either completed remediation or have had their ACM cladding systems removed. It is our ambition that all remaining building owners have works on site by the end of 2020, with completion of remedial works by the end of 2021.

The Government will provide £1 billion in 2020/21 to support the remediation of unsafe non-ACM cladding systems on high-rise residential buildings in both the private and social sectors.