To ask the Secretary of State for Health and Social Care, what the estimated cost to the public purse is of (a) replacing and (b) relocating the Linear Accelerators on the Mount Vernon site to another location, and if he will make a statement.
A
Answered by: Jo Churchill
Answered on: 11 February 2020

The estimated cost to replace a Linear Accelerator in its current location is approximately £1.5 million. Relocation costs vary depending on preparations required and where the Linear Accelerator is being relocated to. Relocation to a site with a ready-to-use bunker could cost around £1.5 million per Linear Accelerator. Relocation to a new site could cost substantially more, and would depend on a number of factors including, acquisition of land and the building of bunkers.

As part of the Mount Vernon Strategic Review, a range of options will be developed to improve travel times for patients requiring radiotherapy.