Crossrail 2 Line:Written question - 174657

Q
(Wimbledon)
Asked on: 13 September 2018
Department for Transport
Crossrail 2 Line
Commons
To ask the Secretary of State for Transport, what the timetable is for the Crossrail 2 independent affordability review.
A
Answered by: Joseph Johnson
Answered on: 15 October 2018

The Crossrail 2 Independent Affordability Review, chaired by Mike Gerrard, has provided interim recommendations to the Secretary of State for Transport and Mayor of London this summer, including recommendations for further work to ensure the scheme taken forward is affordable. Further work is now being taken forward to inform the next steps for the project and complete the Review.

Following the additional work, we expect to publish the findings of the Gerrard Review in due course.