High Speed 2 Railway Line: Eddisbury:Written question - 35453

Q
(Eddisbury)
Asked on: 25 April 2016
Department for Transport
High Speed 2 Railway Line: Eddisbury
Commons
To ask the Secretary of State for Transport, whether any aerial surveys have been carried out in Eddisbury constituency in relation to the High Speed 2 project in 2015 and 2016.
A
Answered by: Mr Robert Goodwill
Answered on: 04 May 2016

Aerial surveys were undertaken in this area in 2015 to capture photography, video and topographical information. Additional surveys will be undertaken in 2016 to capture hyperspectral data.