Aircraft Carriers:Written question - 33852

Q
(Romford)
Asked on: 13 April 2016
Ministry of Defence
Aircraft Carriers
Commons
To ask the Secretary of State for Defence, what recent progress has been made on the construction and procurement of HMS Prince of Wales and the accompanying aircraft for both Queen Elizabeth Class aircraft carriers; and if he will make a statement.
A
Answered by: Mr Philip Dunne
Answered on: 19 April 2016

The construction, test and commissioning of HMS QUEEN ELIZABETH and HMS PRINCE OF WALES continues in Rosyth. Around 80% of the structure of HMS PRINCE OF WALES has been built, and she will be structurally complete this summer. Aircraft will continue to be purchased incrementally, as part of a coherent build-up of capability, and we remain on track to deliver an Initial Operating Capability in the Carrier Strike role from 2020.