Radiotherapy:Written question - 227043

Q
(Northampton South)
Asked on: 10 March 2015
Department of Health
Radiotherapy
Commons
To ask the Secretary of State for Health, what his most recent estimate is of the likely cost of (a) construction and (b) annual operation of the proton beam therapy centre at University College, London.
A
Answered by: Jane Ellison
Answered on: 17 March 2015

The Full Business Case for the University College London Hospitals indicates that the cost of construction will be £138.6 million and the annual operating costs (at full capacity) to be up to £25.5 million per year.